#28PFC Capacitor Bank Step Current & Detuned Harmonic Reactor Audit
Multi-Asset / Multi-Point Equipment Schedule
Inspect multiple transformers, panels, rooms, motors, or RCDs in this module without overwriting previous assets. Each item receives a permanent QR Sticker UID preserved across annual audits.
Sticker UID: OC-CAPA-1C28Standard Limits, Equations & Space Presets
IEC 60831-1, EN 61921, and IEEE Std 18 govern LV shunt power capacitors and detuned harmonic filter banks. Series detuning reactors (p = 5.67%, 7%, 14%) boost capacitor terminal voltage by 1/(1 - p), requiring >= 440 V or 480 V rated cans on a 400 V bus.
Measured Inputs
Calculated / Evaluated Results
Evaluates LV Power Factor Correction (PFC) capacitor steps accounting for Capacitor Nameplate Voltage U_CN (e.g. 440 V / 480 V / 525 V) AND series harmonic detuning reactor factor p (0%, 5.67%, 7%, 14%): Q_eff = [Q_CN / (1 - p)] x (U_L / U_CN)^2, capacitor terminal voltage rise U_C = U_L / (1 - p), dielectric capacitance loss (> -10% = FAIL per IEC 60831-1), and monthly inductive/capacitive utility reactive penalty limits.
Pending / Not tested — results stay neutral until valid measured values are entered.
- Pending
Effective Step Output Q_eff & Expected Current I_nom
-
Q_eff = [Q_CN / (1 - p)] x (U_L / U_CN)^2; I_nom = (Q_eff x 1000) / (sqrt(3) x U_L) per IEC 60831-1.
- Pending
Capacitor Terminal Voltage Stress U_C = U_L / (1 - p)
-
Not tested - enter the measured value. Acceptance: Steady-state capacitor voltage U_L / (1 - p) <= rated U_CN (e.g. >= 440 V for 7% reactor on 400 V bus) [IEC 60831-1 §20 / EN 61921]
- Pending
Step Current / Capacitance Retention Deviation
-
Not tested - enter the measured value. Acceptance: -10% <= Delta_I <= +30% (> -10% loss indicates degraded capacitor film; > +30% exceeds IEC 60831-1 thermal current limit) [IEC 60831-1 §7 & §13 / IEEE Std 18]
- Pending
Step 3-Phase Current Unbalance (L1 / L2 / L3)
- %
Not tested - enter the measured value. Acceptance: Phase unbalance <= 5.0% (higher unbalance indicates open/degraded single-phase capacitor element or pitted contactor pole) [ANSI/NETA MTS §7.20 / IEC 60831-1]
- Pending
Harmonic Detuning Reactor Core / Coil Temperature
- degC
Not tested - enter the measured value. Acceptance: Reactor temperature <= 115 degC continuous alarm threshold (verify klixon thermal cutout wiring) [IEC 60076-6 / EN 61558-2-20]
- Pending
Monthly Utility Inductive Reactive Ratio (E_ind / E_active)
- %
Not tested - enter the measured value. Acceptance: Inductive reactive energy ratio <= 20.0% of active kWh (cos phi >= 0.9806 utility penalty boundary) [TR EPDK Reactive Tariff / EN 50160]
- Pending
Monthly Utility Capacitive Reactive Ratio (E_cap / E_active)
- %
Not tested - enter the measured value. Acceptance: Capacitive reactive energy ratio <= 15.0% of active kWh (prevent night/weekend over-compensation) [TR EPDK Reactive Tariff / IEC 60364-8-1]
Verification Checklist (0 / 13)
1LOTO caution observed: waited >= 3 minutes (or OEM discharge time) after de-energizing and verified < 50 V DC across capacitor terminals before touching [IEC 60831-1 §22]
2Permanent discharge resistors intact and securely connected across every capacitor unit
3No cylindrical capacitor can bulging, top-cap overpressure disconnector activation, resin leakage, or terminal discoloration
4Capacitor rated voltage U_CN (440 V / 480 V / 525 V) properly coordinated with series detuning reactor factor (7% / 14%) and busbar voltage
5Series harmonic detuning reactors installed where busbar THDi > 15% to prevent parallel resonance with the supply transformer
6Reactor thermal NC switches (Klixon bimetal) wired in series with step contactor coils to trip overheated steps automatically
7Capacitor-duty contactors (AC-6b with pre-insertion damping resistors) or zero-crossing thyristor (SVG/SVC) switches free of contact welding
8HRC step protection fuses (gG >= 1.6x to 1.8x I_nom) or MCCBs properly sized and free of single-phasing / thermal browning
9Reactive Power Relay (RPR) CT ratio, phase association (L1/L2/L3 polarity), and target cos(phi) = 0.98-1.00 verified
10Shunt reactor (inductive SVC step) or LED/UPS night-load compensation verified where off-shift capacitive export approaches 15%
11Forced cabinet ventilation fans, dust filters, and enclosure thermostat (<= 40 degC internal ambient) clean and operational
12Infrared thermography survey completed on fuse holders, contactor lugs, reactor links, and capacitor bushings under load
13Automatic PFC disconnect interlock wired to open capacitor steps during emergency generator or transformer switching if required